Construction Of Marine Jetty 1 For Stolthaven Storage Terminal Phase 1A, Jurong Island.

Completed on June 2011

Stolthaven Terminal Jetty 1 at Jurong Island, Singapore is built to berth vessels from 1,000DWT to 45,000DWT. The 200m long Jetty structure is supported by 84 nos of Steel Pipe Piles 762 mmOD with wall, thickness of 16mm, 11 of which are required to be socketed into rocks between 4m to 7.5m drill.

Antara Koh Pte Ltd was contracted by Stolthaven Singapore Pte Ltd in November 2010 for the construction of the Jetty. The components of the Jetty include 1 Loading Platform, 1 Fire Pump House, 3 Berthing Dolphins and 4 Mooring Dolphins. Our scope of work also consists of M&E and Dredging works.

Antara Koh Pte Ltd successfully delivered the Jetty with good quality works, ahead of schedule and on budget. We also achieved no lost time accident for a total of 136,950 manhours. During construction, Antara Koh Pte Ltd coordinated with the top-side contractor to provide access for installation of piping and jetty furniture.

project
Stolthaven Jetty, Tembusu
 
projectStolthaven Jetty, Tembusu
 
project
Top view of Stolthaven Jetty, Tembusu
 
project
Front view of Stolthaven Jetty, Tembusu
 
project
Launching 50 ton precast concrete beam
 
project
Testing and commissioning QRH Captain
 
 
 
Back to top
 
 

 

Think. Discuss. Organise. Do It Right The First Time